📘 CodingMarble Learn

Departmental and Product Costing: Job-Order and Process Costing

Step two and three of cost calculation: share factory overhead between departments, then find the cost of each product. Job-order costing gives each customer order its own cost: direct material + direct labour + overhead by rate. Departmental costing uses a separate overhead rate for each department, which is fairer. Process costing is for goods made all day in the same way: total cost of a department ÷ equivalent units gives cost per unit.

🎬 Step-by-step story

  1. Job-order costing: one customer order is one job. Job A uses direct material 100 and direct labour 120. Direct cost = 220. Overhead is still missing.
  2. One plant-wide rate: overhead 600 ÷ 300 labour hours = 2 per hour. Job A used 40 hours, so overhead is 80. Job cost = 300.
  3. Departments differ. Cutting costs 400 over 100 machine hours = 4 per hour. Assembly costs 300 over 150 labour hours = 2 per hour. Job A: 10 × 4 + 25 × 2 = 90. Job cost = 310.
  4. Process costing: a department spends 900. It finished 160 units and left 40 units half done. Equivalent units = 160 + 20 = 180. Cost per unit = 900 ÷ 180 = 5.
  5. Which method? Custom orders (each job different cost) use job costing. Same goods made all day (flour, cement) use process costing: each unit costs the same.
  6. Your turn: slide cutting machine hours and assembly labour hours. See how the overhead and the job cost change.

Tip: drag the 3D scene to turn it. Use two fingers to zoom.

🤔 Common doubts, cleared

Why not simply charge each job the real overhead?

We only know the real bill at year end. A rate lets us price jobs on time. The small difference is adjusted later.

Why do departments get their own rates?

Cutting has costly machines (4 per hour) and assembly does not (2 per hour). Job A is charged 90, not 80, because it uses machine time.

What are equivalent units?

Partly finished units converted into full-unit work. 40 units at 50% equal 20 full units.

Why is cost per unit the same in process costing?

Identical units are made together, so cost is shared equally. In job costing every job gets its own cost.

Does departmental costing change the direct cost?

No. Only overhead is shared differently. Direct cost stays 220 in both ways.

Job-order costing and overhead

Job-order costing is used when each order is different (custom furniture, printing, repair). A job cost sheet collects: direct material, direct labour and a share of factory overhead.

Overhead cannot be traced to a job, so we use an overhead rate:

Overhead rate = Overhead pool ÷ Base (for example direct labour hours or machine hours).

Overhead charged to a job = rate × the base used by that job. We use budgeted figures at the start of the year, so jobs can be priced early. The small difference with the real overhead is adjusted at year end.

Departmental job-order costing

Factories have departments that work very differently. A cutting department with costly machines has more overhead per hour than a hand assembly department. One plant-wide rate would hide this.

Departmental costing has three steps:

  1. Allocate or share overhead to departments (rent by floor area, power by meter, supervisors by number of workers).
  2. Find a rate for each department using its own base (machine hours for cutting, labour hours for assembly).
  3. Charge each job: sum of (rate × hours in that department).

Result: a job that uses costly machines carries more overhead. Prices become fairer.

Process costing

Process costing is used when many identical units pass through steps (flour, cement, soap, bottles). We cannot cost one unit alone, so we find the cost of a period for a department and share it over the units.

Some units are only partly done at the end. We turn them into equivalent units: units × percent complete. Example: 40 units that are 50% done equal 20 full units.

The finished units pass to the next department or to the store.

Choosing the right method

Job-order costingProcess costing
OutputDifferent ordersIdentical units, continuous
Cost found forEach jobEach department and period
Cost per unitJob cost ÷ units in jobPeriod cost ÷ equivalent units
ExamplesPrinting, shipbuilding, repairsFlour, cement, chemicals

Key formulas and definitions

Worked examples

1. Overhead 600 and 300 labour hours. Find the rate. A job uses 40 hours: overhead charged?

Rate = 600 ÷ 300 = 2 per hour. Charged = 40 × 2 = 80.

2. Job A: material 100, labour 120, overhead 80. Job cost?

100 + 120 + 80 = 300.

3. Cutting: overhead 400, 100 machine hours. Assembly: overhead 300, 150 labour hours. Job A uses 10 machine hours and 25 labour hours. Overhead?

Cutting rate 4, assembly rate 2. 10 × 4 + 25 × 2 = 40 + 50 = 90.

4. Job A with the department rates: job cost?

220 + 90 = 310.

5. Cost 900. 160 finished units, 40 units 50% complete. Cost per unit, finished cost, work-in-progress cost?

Equivalent units = 160 + 20 = 180. Cost per unit = 900 ÷ 180 = 5. Finished = 160 × 5 = 800. WIP = 20 × 5 = 100. Total 900.

6. A job of 50 cards costs 310. Cost per card?

310 ÷ 50 = 6.2 per card.

Common mistakes

Practice quiz

1. Which suits job-order costing?
2. Overhead 800, machine hours 200. Rate is:
3. 40 units, 50% complete, equal how many equivalent units?
4. In departmental costing the rate is found:
5. Cost per equivalent unit =

Practice: answer these yourself

Type or choose your answer, then press Check. Use a hint if you are stuck; the full solution appears after you answer.

Frequently asked questions

What is job-order costing?

A method that finds the cost of each customer order using direct material, direct labour and overhead charged by a rate.

What is the difference between job costing and process costing?

Job costing finds the cost of each different order. Process costing finds the cost of a department's period and divides it by equivalent units.

What are equivalent units?

Units of work expressed as full units. Partly finished units are multiplied by their percentage complete.

Where this is taught

Japan高校(専門学科)1〜3年Cost Accounting

Learn first

Learn next

Related lessons

All Accountancy lessons