📘 CodingMarble Learn

Standard Costing: Purpose, Procedure and Cost Variance Analysis

Standard costing sets what a product should cost (the standard), records what it actually cost, and studies the difference, called a variance. A variance is favourable if actual cost is below standard and unfavourable if above. Splitting the variance by cause shows where money was lost: material price and usage, labour rate and efficiency. Managers use this to find problems early, control cost and plan better.

🎬 Step-by-step story

  1. Standard card: one unit needs 2 kg of material at 10 per kg. For 100 units the standard is 200 kg × 10 = 2,000.
  2. Actual: the factory used 230 kg and paid 9 per kg = 2,070. Actual − standard = 70 more than planned. This total variance is unfavourable.
  3. Split it. Price variance = (10 − 9) × 230 = 230 favourable (cheaper kg). Usage variance = (200 − 230) × 10 = 300 unfavourable (30 kg extra). Net 70 unfavourable.
  4. Labour: standard 100 hours at 20 = 2,000. Actual 110 hours at 22 = 2,420. Rate variance = (20 − 22) × 110 = 220 unfavourable. Efficiency variance = (100 − 110) × 20 = 200 unfavourable.
  5. By cause: cheaper cloth (230 saved) but poor quality wasted material (300 lost); overtime pay (220) and slow work (200). Net 490 unfavourable. Each bar points to one cause to fix.
  6. Your turn: slide the actual kg and the actual price. See the price and usage variances move on their own.

Tip: drag the 3D scene to turn it. Use two fingers to zoom.

🤔 Common doubts, cleared

Why is price variance found with actual quantity?

Because the price difference applies to every kg that was really bought. Usage uses the standard price, to keep the two parts separate and adding up.

Is 'favourable' always good news?

Not always. A cheap supplier gave 230 F but waste cost 300 U. Look at the pair and the cause.

Why is standard quantity for actual output?

We must compare like with like. If the factory makes 100 units, the allowed quantity is for 100 units, not for a different plan.

Why do the parts add up to the total?

230 F − 300 U = 70 U, which is exactly actual cost minus standard cost. Try changing the sliders.

Who should fix a labour rate variance?

Usually planning and HR, because it comes from pay rates and overtime, not from speed of work.

Purpose and procedure of standard costing

Standard cost is the planned cost of one unit under normal, efficient work. It is set before production using past records, time studies and supplier quotes.

Why use it?

Procedure:

  1. Set standards (quantity and price for material, hours and rate for labour, overhead).
  2. Record the actual cost.
  3. Compare to find variances.
  4. Analyse the causes.
  5. Report to managers and act.

A standard cost card lists all standards for one unit.

Material cost variances

A variance is the difference between standard and actual. Mark it F (favourable, profit rises) or U (unfavourable, profit falls).

Standard quantity means the quantity allowed for the actual output made.

Labour cost variances

Overhead variances follow the same idea: spending (paid more than planned) and efficiency or volume (used time or capacity differently from plan).

Reading variances: by cause and action

A variance only helps if someone acts on it.

VarianceLikely causeWho acts
Material priceSupplier or buying choicePurchasing
Material usageWaste, qualityProduction, quality control
Labour rateOvertime, pay gradeProduction planning, HR
Labour efficiencySkill, machinesSupervisors

Causes can link: a cheap material (price F) may raise waste (usage U). Look at the pair together, and report only large variances (management by exception).

Key formulas and definitions

Worked examples

1. Standard: 2 kg at 10 per unit. What is the standard material cost for 100 units?

Standard quantity = 200 kg. 200 × 10 = 2,000.

2. Actual: 230 kg at 9. Find the actual cost and total variance.

Actual = 230 × 9 = 2,070. Variance = 2,000 − 2,070 = 70 unfavourable.

3. Find the material price and usage variances.

Price = (10 − 9) × 230 = 230 F. Usage = (200 − 230) × 10 = 300 U. Total = 230 − 300 = 70 U.

4. Labour: standard 100 hours at 20; actual 110 hours at 22. Find rate, efficiency and total.

Rate = (20 − 22) × 110 = 220 U. Efficiency = (100 − 110) × 20 = 200 U. Total = 420 U. Check: standard 2,000, actual 2,420, difference 420.

5. Add all four variances. What is the net result?

Price 230 F − usage 300 − rate 220 − efficiency 200 = −490, so 490 unfavourable.

6. A bakery: standard 100 kg flour at 5, actual 110 kg at 4.8. Price, usage and total variance?

Price = (5 − 4.8) × 110 = 22 F. Usage = (100 − 110) × 5 = 50 U. Total = 28 U. Check: actual 528 − standard 500 = 28.

Common mistakes

Practice quiz

1. Actual cost is lower than standard cost. The variance is:
2. Material price variance uses:
3. A rise in overtime pay causes mainly a:
4. SQ 50, AQ 55, SP 4. Usage variance =
5. First step of standard costing:

Practice: answer these yourself

Type or choose your answer, then press Check. Use a hint if you are stuck; the full solution appears after you answer.

Frequently asked questions

What is standard costing?

A system that sets a planned cost per unit, compares it with actual cost and studies the differences (variances) to control cost.

What is a favourable variance?

A variance where actual cost is below standard cost, which raises profit.

What are the main cost variances?

Material price and usage, labour rate and efficiency, and overhead spending and efficiency or volume variances.

Where this is taught

Japan高校(専門学科)1〜3年Cost Accounting

Learn first

Learn next

Related lessons

All Accountancy lessons