Basics of Construction Planning

A construction plan answers four questions: what will we build, in what order and how long, what helps us build it, and what will it cost. It has a time chart of tasks, a plan for temporary works like scaffolds and formwork, a specification of materials and quality, and an estimate: quantity × price.

🎬 Step-by-step story

  1. Be clear about the goal: a 6 m by 4 m store shed. Planning starts from the goal.
  2. The work plan puts jobs on a time chart. Dig first, then footing, then walls, then roof. Each job starts after the one before.
  3. Temporary works are scaffold, formwork, fence, site shed and road. They are not part of the building. They help the work and are removed at the end.
  4. The specification says what and how: the concrete mix, the brick size, the roof sheet. Without it, each worker builds as he likes.
  5. The estimate is quantity times price. Footing concrete is perimeter × width × depth. Wall is perimeter × height minus the door. Add the costs.
  6. Your turn. Change the length and width. The quantities and the cost change by themselves.

Tip: drag the 3D scene to turn it. Use two fingers to zoom.

🤔 Common doubts, cleared

Why do we write the goal first?

Every later choice, the jobs, the order and the cost, depends on what we are building and how big. The shed in step 0 is the goal.

Why can't the walls start on day 1?

Walls stand on the footing. The footing must be dug, poured and hardened first. The bars in the chart start one after another.

Why remove scaffold and formwork?

They only help the work. Once the concrete has hardened and the work is finished they are not needed, and they can be used again. Press the button to remove them.

Why do we need a specification when we have a drawing?

A drawing shows shape and size but not the quality. The tags in step 3 show what the drawing cannot say.

Why subtract the door from the wall area?

There is no brick where the door is, so we pay only for the wall that is built.

What happens to the cost if I make the shed bigger?

Concrete and wall quantities grow with the perimeter, so the cost goes up. Move the sliders and watch.

Drafting a construction plan

A construction plan turns drawings into a job that can be done. Steps to draft it:

  1. Study the goal and the drawings: size, place, materials, date needed.
  2. Break the work into tasks: dig, footing, walls, roof, finishing.
  3. Fix the order: a task that needs another must wait. Walls cannot start until the footing has hardened.
  4. Estimate the time for each task from the quantity and how much a team does per day.
  5. Draw a bar chart (Gantt chart): each task is a bar, its length is its days, its place shows when it starts.
  6. Plan the resources: workers, tools, materials and when they must arrive.

Weather matters. In farm areas, plan concrete work for the dry season and allow spare days.

Temporary works planning

Temporary works are things we build only to make the job possible or safe. They are removed when the job ends. Examples:

Plan where each goes, who builds it, how strong it must be (a scaffold must carry workers and materials), and when it is removed. Temporary works cost money and time, and many accidents come from badly built ones, so they are part of the plan and the cost.

Specifications

A specification is a written description of the quality of materials and of the work. The drawing shows where and how big; the specification says what and how good.

It includes: the material and grade (cement type, concrete mix 1:2:4, steel grade), sizes (brick size, bar diameter), how to do the work (mix, pour, cure for 7 days), tests to pass, and the standard or code to follow. Example lines: "Footing concrete 1:2:4, 0.4 m wide, 0.4 m deep, cured 7 days" and "Walls in first-class brick, 230 mm thick, cement mortar 1:6".

It is part of the contract, so the buyer, the builder and the inspector all agree on the quality.

Cost estimation

An estimate is a calculated guess of the cost before building. Steps:

  1. Take off quantities from the drawings: concrete in m³, wall in m², steel in kg, roof in m².
  2. Choose unit prices (rates): price per m³, m², kg or day of labour.
  3. Multiply: cost of an item = quantity × rate.
  4. Add: total of all items, plus temporary works, plus a small allowance for waste and surprises (contingency), plus the contractor's overhead and profit.

Example: footing concrete = perimeter 20 m × 0.4 m × 0.4 m = 3.2 m³. At 6000 per m³ this costs 19 200. Wall = 20 × 2.5 m − 2 m² (door) = 48 m². At 800 per m² this costs 38 400. Together 57 600 before the extras.

Estimates also help us compare designs and decide what we can afford. Compare the estimate with the real cost later to improve the next estimate.

Try it: plan a tent

Plan putting up a small tent at home. List the tasks (clear the ground, lay the sheet, fix poles, tie ropes). Mark the order. Give each a time. Draw a bar chart on squared paper. What helps you but is not the tent itself? (A stool, a rope marker, a torch.) Those are your temporary works.

Key formulas and definitions

Worked examples

1. Dig takes 2 days, footing 3 days, walls 4 days and roof 2 days, one after the other. How many days does the job take?

2 + 3 + 4 + 2 = 11 days.

2. A footing strip has perimeter 20 m, width 0.4 m and depth 0.4 m. Find the concrete volume.

20 × 0.4 × 0.4 = 3.2 m³.

3. Concrete costs 6000 per m³. Find the cost of 3.2 m³.

3.2 × 6000 = 19 200.

4. A shed has perimeter 20 m, wall height 2.5 m and one door of 2 m². Find the wall area.

20 × 2.5 = 50 m². Subtract the door: 50 − 2 = 48 m².

5. Wall costs 800 per m². Find the cost of 48 m² and the total with the 19 200 concrete.

48 × 800 = 38 400. Total = 19 200 + 38 400 = 57 600.

6. Add 5% for waste and surprises to a total of 57 600. What is the new total?

5% of 57 600 = 2 880. New total = 57 600 + 2 880 = 60 480.

7. A team does 12 m² of brick wall per day. How many days for 48 m²? If the roof can only start after the walls, and roof takes 2 days, what is the total for these two jobs?

48 ÷ 12 = 4 days for walls. The roof starts after, so total = 4 + 2 = 6 days.

Common mistakes

Practice quiz

1. A bar chart shows:
2. Which is a temporary work?
3. A specification tells us:
4. Cost of an item equals:
5. Formwork is used to:

Practice: answer these yourself

Type or choose your answer, then press Check. Use a hint if you are stuck; the full solution appears after you answer.

Frequently asked questions

What are temporary works in construction?

Things built only to help the job and removed later, like scaffold, formwork, fences, site sheds and access roads.

What is the difference between a drawing and a specification?

The drawing shows where and how big. The specification says what material, what quality and how the work is done.

How do you estimate the cost of a building?

Take quantities from the drawings, multiply each by its unit rate, add them, then add temporary works, a small allowance and the contractor's profit.