📘 CodingMarble Learn

Design of Reinforced Concrete Structures

Concrete is strong when squeezed but weak when pulled. In a beam, the top is squeezed and the bottom is pulled, so steel bars go near the bottom. The squeezing force C in the concrete and the pulling force T in the steel are equal, and together they make the moment capacity M = T × arm. Columns are mainly squeezed. Prestressed concrete squeezes the beam in advance so that cracks do not open.

🎬 Step-by-step story

  1. A plain concrete beam bends under load. The bottom is stretched and black cracks open. Concrete is weak when pulled.
  2. We put steel bars (rebar) near the bottom. The bars take the pull, so the cracks shrink.
  3. Look at the section. The top block (red) is squeezed (C). The bars (blue arrow) are pulled (T). C and T are equal.
  4. Add more bars. Watch the moment capacity M grow. When M is above the demand, the beam is safe.
  5. Prestressing: strong cables squeeze the whole beam before any load. Now the cracks are shut tight.
  6. Your turn. Slide the number of bars and see when the beam becomes safe.

Tip: drag the 3D scene to turn it. Use two fingers to zoom.

🤔 Common doubts, cleared

Why do cracks open only at the bottom?

When the beam sags, the bottom is stretched and plain concrete cannot take the stretch.

Do the bars stop the cracks completely?

No. Tiny cracks still form, but the bars keep them narrow and the beam does not break.

Why is C equal to T?

Nothing slides sideways, so the squeeze and the pull must cancel along the beam.

More bars means more strength. Is there a limit?

Yes. With too many bars the concrete block gets very deep and crushes before the steel yields. That is a sudden, bad failure.

Where do the green arrows come from?

They are the prestressing cables pulling and squeezing the beam from both ends.

What does the label above the beam tell me?

It shows the moment capacity in kNm and says SAFE if it is at least the 150 kNm demand.

Design methods for reinforced concrete

Reinforced concrete (RC) is concrete with steel bars inside. Concrete has a compressive strength fc (for example 25 MPa) but its tension strength is only about a tenth of that. Steel (rebar) has a yield strength fy (for example 500 MPa) and takes all the pull.

The modern way is limit state design. We increase the loads with load factors, then check that the member strength (reduced by safety factors) is bigger. Two limits are checked: strength (it must not break) and serviceability (cracks and sag must be small). The old working stress method instead kept stresses under allowed values.

Steel needs cover, a layer of concrete outside it (about 25–40 mm). Cover protects steel from rust and fire.

Design of beam structures

In a beam section (width b, effective depth d from the top to the centre of the bars) there are two forces. The concrete near the top gives a squeezing force C = 0.85 fc × b × a, where a is the depth of the squeezed block. The steel gives a pull T = As × fy.

Balance: C = T, so a = As fy / (0.85 fc b). The pair C and T make a couple with arm (d − a/2). So the moment capacity M = As fy (d − a/2).

To design: find the moment M from the loads, then find As ≈ M / (fy × 0.9 d), choose bars, and check. Too much steel is dangerous: the concrete crushes suddenly before the steel yields. Too little steel makes the beam crack and fail suddenly too. Add stirrups (loops of bar) to resist shear near the supports.

Design of column structures

A column mainly takes squeezing from the floors above. Concrete takes most of it and the vertical steel bars help. A simple short-column formula is P = 0.4 fc Ac + 0.67 fy Asc, where Ac is the concrete area and Asc the steel area.

Rules of thumb: steel is 0.8% to 4% of the section. The vertical bars are held by ties (rings) so they do not bulge outward. A tall slim column can buckle (bend sideways), so its strength is reduced for slenderness. Columns also feel bending when beams push on one side.

Design of prestressed concrete structures

In prestressed concrete, high-strength steel cables (tendons) are pulled tight and then anchored, so they squeeze the concrete before any load comes. The load then first has to cancel this squeeze before the concrete can be stretched. So the beam stays uncracked, can be thinner, and can span farther.

Net stress at the bottom: σ = P/A + P e y / I − M y / I in simple terms, prestress squeeze minus load stretch. If the answer is still squeeze (positive), there is no crack. Prestress is lost slowly over time (concrete shrinks and creeps, steel relaxes), so designers allow about 15–25% losses.

Pre-tensioning pulls the cables first and pours concrete around them (in factories). Post-tensioning pulls cables in ducts after the concrete hardens (on site).

Try it

At home: take a dry sponge or a block of chalk and bend it: it cracks at the stretched side. Now squeeze a row of books and lift them: that is prestress.

In the 3D: find the smallest number of bars that makes the label say SAFE (demand is 150 kNm).

Key formulas and definitions

Worked examples

1. Find the steel area of three 20 mm bars.

One bar: π × 20² / 4 = 314 mm². Three bars: 3 × 314 = 942 mm².

2. Beam b = 300 mm, f_c = 25 MPa, f_y = 500 MPa, A_s = 942 mm². Find the compression block depth a.

a = 942 × 500 / (0.85 × 25 × 300) = 471 000 / 6375 = 73.9 mm.

3. Same beam, d = 450 mm. Find the moment capacity.

M = 942 × 500 × (450 − 73.9/2) = 471 000 × 413.05 = 194.5 × 10⁶ N·mm = 194.5 kNm.

4. Design moment is 150 kNm, d = 450 mm, f_y = 500 MPa. Estimate A_s and the number of 20 mm bars.

A_s ≈ 150 × 10⁶ / (500 × 0.9 × 450) = 741 mm². Bars = 741 / 314 = 2.36, so use 3 bars (942 mm²).

5. A short column 300 × 300 mm has 1440 mm² of steel. f_c = 25, f_y = 500. Find its load capacity.

A_c = 90 000 − 1440 = 88 560 mm². P = 0.4 × 25 × 88 560 + 0.67 × 500 × 1440 = 885.6 kN + 482.4 kN = 1368 kN.

6. Bottom fibre: the load stretches by 10 MPa, the prestress squeezes by 12 MPa. Will it crack?

Net = 12 − 10 = 2 MPa squeeze. It is still squeezed, so no crack.

Common mistakes

Practice quiz

1. Concrete is weak in:
2. In RC beam design, C equals:
3. Prestressing mainly does this:
4. Ties in a column:
5. Cover protects steel from:

Practice: answer these yourself

Type or choose your answer, then press Check. Use a hint if you are stuck; the full solution appears after you answer.

Frequently asked questions

Why do steel and concrete work together so well?

They grip each other, they expand almost equally with heat, and concrete protects steel from rust.

Does a bigger beam always need more steel?

No. A deeper beam has a longer arm (d), so it needs less steel for the same moment.

Why use prestressed concrete?

It stays uncracked, uses less material and spans longer distances, like on bridges.

Where this is taught

Japan高校(専門学科)1〜3年Civil Structural Design

Learn first

Learn next

Related lessons

All Physics lessons