📘 CodingMarble Learn

Production Planning and Management

Production planning decides what to make, how much, when and with which machines and materials. Production management runs the plan day by day, watches progress and fixes delays. Production and distribution means the goods are stored and sent to customers on time.

🎬 Step-by-step story

  1. A factory has four places: materials, a machine, a store and delivery. Goods must pass through all four.
  2. First comes the plan. The board shows who works when: materials first, then the machine, then the store.
  3. Now management starts the work. Crates move from place to place, following the plan.
  4. The machine is too slow here. Crates pile up in front of it. This slow place is a bottleneck. Managers find it and fix it.
  5. Finished goods leave the store and the truck takes them to customers. Distribution is the last step.
  6. Your turn. Change the orders and the machine speed. Can you finish on time?

Tip: drag the 3D scene to turn it. Use two fingers to zoom.

🤔 Common doubts, cleared

Why plan before making anything?

Without a plan, materials or machines may not be ready, and orders may be late or too many goods are made.

Is management only watching the workers?

No. It makes sure materials, machines and people are ready, and fixes problems as they come.

Why do crates pile up in front of the machine?

The machine takes crates slower than they arrive, so the extra waits in a queue. That is a bottleneck.

Why include delivery in production?

Customers only gain when goods reach them, so delivery time must be part of the plan.

How do I know if I will be late?

Compare orders with capacity (speed x days) in the free play readout.

Production planning

Production planning is deciding before you start. It answers five questions: What will we make? How many? By when? With which machines and people? With which materials? The planner looks at customer orders and at the stock already in the store. The result is a schedule, a time table that says which job runs on which machine and when.

Planners also check capacity, the most a machine or line can make in a given time. If orders are more than capacity, they add shifts, add machines, or tell the customer a later date.

Production management

Production management is running the plan every day. Managers make sure materials arrive, machines are ready, workers know their jobs and the work follows the schedule. They compare what is done with what was planned. If something goes wrong, they act. A common problem is a bottleneck: the slowest step, which holds up everything after it. The whole line can only go as fast as the bottleneck. Making it faster, or adding another machine there, speeds up the whole line.

Managers also balance quality, cost and delivery time, because speeding up can hurt quality.

Production and distribution

Distribution is getting finished goods to customers. Goods are counted, packed, stored and loaded. Good planning keeps enough stock to meet orders but not so much that money and space are wasted. Delivery is planned too: which truck, which route, which day. If production is late, delivery is late, so the two must be planned together.

Try it

In the 3D, set orders to 18 and machine speed to 2. Are you late? Raise the speed until you are on time. Then think of something at home you make in steps, like a school lunch. Which step is the bottleneck?

Key formulas and definitions

Worked examples

1. A machine makes 8 parts a day. A customer orders 40 parts. How many days are needed?

Days = 40 / 8 = 5 days.

2. A line has three steps that make 10, 6 and 9 items per hour. How many items per hour can the whole line make? Which step is the bottleneck?

The line makes only 6 per hour, the speed of the slowest step. The step with 6 is the bottleneck.

3. You get an order for 90 chairs in 6 days. Your workshop makes 12 chairs a day. Can you finish on time? What can you do?

Capacity = 12 x 6 = 72 chairs. That is less than 90, so you will be late by 18 chairs. Add a second shift, hire help, or ask for a later date.

Common mistakes

Practice quiz

1. Production planning decides:
2. A bottleneck is:
3. A time table of jobs on machines is a:
4. A machine makes 7 parts a day. How many in 4 days?
5. Distribution means:

Practice: answer these yourself

Type or choose your answer, then press Check. Use a hint if you are stuck; the full solution appears after you answer.

Frequently asked questions

What is the difference between production planning and production management?

Planning decides what to do before work starts. Management runs the plan every day and fixes problems.

What is a bottleneck in production?

It is the slowest step in the line. All the steps after it must wait, so the whole line runs at its speed.

Why is distribution part of production?

Goods are only useful when they reach the customer, so delivery must be planned with production.

Where this is taught

Japan高校(専門学科)1〜3年Industrial Management Technology

Learn first

Learn next

Related lessons

All Business Studies lessons